Project assignment defaults to zero for Project Resource planning

This update includes an enhancement for the Project Resource planning functionality.

In the past, when a resource was assigned to a project, project assignment was automatically set based on the user’s calendar-based availability. This resulted in user's overload when the user was assigned to more than one project.

To address this issue, starting with this update, when a user is assigned to a project, project assignment defaults to 0 and must be explicitly set by a Project manager.

Note: Project assignment is reset to 0 for existing project assignments, unless the value has been manually changed. As a result, if work has been assigned at the tasks level, and the project assignment has not been manually changed, project assignment now defaults to 0, and user is displayed as overloaded.