Sprint by Sprint Roadmap View

See a sprint-by-sprint Roadmap of your Tasks. When synced with Clarizen One, you can create reports that give you the following status across projects/products, or per project/product:

  1. Which tasks are due in each sprint, and when the sprint is due?
  2. How much work do we have in each sprint?
  3. Which projects/products are addressed in each sprint?
  4. Are we on track?

Option 1 - View by sprint name (X axis = “Parent Milestone” or “Clarizen Go Board”)

mceclip0.png

Option 2 - View by sprint due date (X axis = “Parent Milestone Due date”)

mceclip2.png

mceclip3.png

Before you begin

All Clarizen Go reports require syncing between Clarizen Go and Clarizen One. Here is how to set this up for your account.

Setup in Clarizen Go

Clarizen Go Object

What to do

Examples

Workspace

Create Workspaces for each of your projects / products.

Workspace 1: “Product A”;

Workspace 2: “Product B”

Make sure the Workspace is synced with Clarizen One (enable ”Sync with Clarizen One” in the Workspace settings)

 

Boards

Add Boards in the Workspace for your backlog and each of your sprints

Board 1: “Backlog”

Board 2: “Sprint 1”

Board 3: “Sprint 2”

Milestones

Add Milestones in the Workspace for each of your sprints. They will be used to capture the sprints’ end dates.

Milestone 1: “End of Sprint 1 - 5/14/2019”

Milestone 2: “End of Sprint 2 - 5/28/2019”

Tasks

Add Tasks to Boards: Add Tasks to the Backlog board, and move them to the Sprint Boards as you plan your sprints

 

Connect Tasks to Milestones to set their Due date

Connect all Tasks in Sprint 1 to the Milestone “End of Sprint 1”

Enter an Effort Estimation per task

 

Define a Priority per Task

 

As work gets done, move tasks across Stages on the Board. This will also set the tasks’ Status

Stage 1: To Do
Stage 2: In Progress
Stage 3: Done

-

In Clarizen One, use these fields (which are updated by Clarizen Go):

Field Level

Clarizen Go Field →

Updates this Clarizen One Field

Project

Workspace Name

Project Name

Milestone

Milestone Name (reflects the sprint name: “End of sprint 1”, etc.)

Milestone Name

Milestone Date (reflects the sprint’s end date)

Milestone End Date

Task

Task Name

Task Name

Task’s Milestone

Task’s parent Milestone

Task Effort Estimation

Task Work

Task Priority

Task Importance

Task Due date (=set by the task’s Milestone)

Task Due Date

Task’s Board

Clarizen Go Board


Install the Clarizen Go Assignee Sync & Best Practice Reports app, and get access to report templates that you can use out of the box or customize as needed.