I would like to add a lead time to a task. Is this possible?

Krystal Brady Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Krystal,

Is the task dependent on another task?  If so, you can set a "lag" when you set the dependency.  This lag can be a negative number, e.g. -7 days, which in effect gives you lead time (the lag will cause the task start date to be the predecessor's due date - 7 days).  

 