Actual cost by user for a project

I am trying to report on actual cost, by manager, for a project.  I want it more detailed than just the manager in charge of the project. I would like to allocate costs across different functions.  Is there any way to do this?  I have tried using the excel add-in but still do not see a way to get it on a more granular level than just the project manager.

Amanda Roth Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Hi Amanda,

You should be able to run a report at the Task level and pull in:

  • Name of task
  • Name of parent project
  • Name of manager
  • Actual cost of task

Summed cost is tied to a task which rolls up to the higher levels.  However, each task has a task manager (not necessarily the project manager) and you could break down the information at this level.

Please hop on our Advanced Q&A webinar for further assistance.-> http://www.clarizen.com/resources/online-demo.html#second

Diana

Diana Sandura 0 votes