How is % completion calculated?

I thought % completion would be actual/(actual + remaining) effort but that is not what I am seeing.  Please clarify this calculation.  thanks

Karen Lewis Answered

Please sign in to leave a comment.

3 comments

0
Avatar

I'll need more details on what you are seeing, that formula should be correct.

Josh Santos 0 votes
Comment actions Permalink
0
Avatar

hi - I have a project with 26 actual and 34.5 remaining. showing 49% but wouldn't the calc be:  26/(34.5 + 26 = 43%?

Karen Lewis 0 votes
Comment actions Permalink
0
Avatar

Do you have empty milestones in the project?  This will change the weight of the sub-items.  There is also a feature called progress impacts that allows you to make some children work items have more weights then others when rolling up to the parent.

Josh Santos 0 votes