Financial indicator color

Hi

I have a project portfolio that shows 19% completes and 3% invested.  I would assume it should be 'green', but Clarizen shows 'orange' indicator.  Can you advise criteria for Green/ Orange/ Yellow for financial indicators?

Thanks for your help in advance.

 

Naomi

Nverci01 Answered

Please sign in to leave a comment.

1 comment

0
Avatar

The financial status indicator is driven by CPI, which factors in % completion, planned budget, and actual costs. If your planned budget is 19% and actual cost is only 3% of your budget, I would think the indicator would be green.  This make require a deeper investigation.  What does CPI say for the item that is orange?  (Green is CPI above 1.0, Orange between 0.7 and 1, and Red below 0.7).

Josh Santos 0 votes