Completed Project remains on Time Tracking Sheet

A completed project remains on my time tracking sheet.  The completion dates are in the future (2014) due to a fat fingered error when project was created.  When will this completed project drop off of my time sheet?  I hope I don't have to wait until July 2014 which is the last date in the project.

Jyl Sheatsley Answered

Please sign in to leave a comment.

1 comment

0
Avatar

I would adjust the due date of the project (can reactivate, fix, close again), otherwise it is going to be there for a while.  You can also quickly filter out completed items from your time tracking view and toggle this on or off as needed (click the magnifying glass next to the instant search in the upper right and you can quickly check/uncheck completed).