how can I use project baselines?

I set baselines for a project and would like to compare actuals to baseline.  How can I do this?

jay sullivan Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Hi Jay,

When you display you Gantt view, you have a picklist with multiple views: standard, critical path, baseline, and plan vs actual.

If you click on the latter it will show you one against the other.

Jonathan Angel 0 votes
Comment actions Permalink