How does a project manager assign an e-mail only resource to an entire project?

The need is for the e-mail only resource to have the same e-mail based task completion reminders and update ability as the project manager, with month by month milestones. Currently, I have only seen an ability to assign resource load one task at a time and we have hundreds of subtasks within each project.

Joseph L Maimone Answered

Please sign in to leave a comment.

1 comment

0
Avatar

You assign email-only users just as you would any other user.  If you want them to be assigned to every task in a project, you could save those users as part of a template (assuming you have similar, repeatable project plans), you could use Ctrl+C and Ctrl+V to quickly paste a users throughout the project, or you could use customizations (hop on an advanced Q&A or talk to your CSM about this option).

Josh Santos 0 votes