Am I using dependencies the wrong way?

I keep assigning dependencies to tasks, yet when I update the start/due date of the leading task, the following one doesn't update.  It doesn't matter what type of dependency I'm assigning; it simply never works...

Jon Riviere Answered

Please sign in to leave a comment.

2 comments

0
Avatar

This is likely due to a manually set date on the successor task (the following tasks).  Do you see any blue triangles in the start date or due dates of successor items?  These manual dates will override the dependency.  I would recommend hopping on any of our Q&A webinars (http://webinars.clarizen.com) to get more tips & tricks on using dependencies.

Josh Santos 0 votes
Comment actions Permalink
0
Avatar

Yep.  I was afraid that's what was causing the problem.   Thanks for the help! 

Jon Riviere 0 votes