How can I make the workload in hours (or other) relating to certain dates?

For instance when the workload is 24H and the start state is set on 13/01/14. Is it possbile when i change the workload to 48H that for instance the estimated date will change to 14/01/14?

Gijs van M Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Yes, in this case I would use fixed work.  Enter in the work (optionally you can enter in the resources' unit utilization), and it will push out the duration. This can be a complicated topic, so I would strongly recommend hopping on a Q&A webinar to go into this in greater detail (http://webinars.clarizen.com)