V6 Resource Conflict

In V6 - which field indicates there is a conflict with a resource's availability to complete work within the date specified.  For instance if I assign 40 hours of work to a resource with a 1 day duration where will I see the conflict?  I searched for conflict in the  instructions but only the V5.4 manual references this.  Thank you.

 

Karen Lewis Answered

Please sign in to leave a comment.

1 comment

0
Avatar

The resource conflict comes up if you try to assign a resource to a task during a time period in which they are not working (on PTO, etc.).  This is no out of the box field that will show this overload (overloading resources is allowed in Clarizen).  However, when you are making resource assignments, you can do a resource load simulation to see if the resource will become overloaded post assignment.  When typing in a resource name, just click the icon next to his/her name.  Also if you are on a team view, you will get a warning message when trying to reassign a task to a resource that would become overloaded.

Josh Santos 0 votes
Comment actions Permalink