How is a baseline established?

When a project is activated? I am using V5 and cannot see where to save a baseline.

Jgrundey Answered

Please sign in to leave a comment.

1 comment

0
Avatar

In V5, you would right click on the project in the Work Plan and select to save as baseline.  In V6 it is an option in the ribbon menu.