Adding columns to Workplan?

I would like to add few columns to the WorkplanEstimated hours, Estimated Cost, Actual hours workedActual Cost.

I have tried to locate the "Estimeted hours, Estimeted Cost, Actual hours worked, Actual Cost" fields in the project and in the milestone, but i couldn't. Maybe you gave them another names, is that right!?

Hanan Melamed Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Estimated Hours is "Work" unless you have a custom field.  Estimated Cost is Budgeted Cost.  Actual Hours and Actual Cost are named exactly that and should be available.  I would use the search function when adding columns to quickly pull up those fields and add them into your view.