Time isn't showing in Project screen scheduling view for Actual effort when you update the date range?

I am in the Project tab, using the scheduling or baseline view, and I have a column called Actual Effort.  I then go up to the date range, and select a month (in this case Feb), shouldn't the hours update on my screen under the Actual Effort column for just the hours in the date range I selected?  Instead I am getting all YTD hours.....

 

Thanks,

Scott

 

Scott Brinser Answered

Please sign in to leave a comment.

1 comment

0
Avatar

No, Actual Effort is not impacted by date ranges.  That is the grand total for the work item you are selecting/looking at.  If you are using Time Tracking, you can run a report that will show the effort for a specific timeframe.