Why do my tasks with linear dependencies change order when I navigate away from the schedule window and return?

I am attempting to create a project schedule. I have certain milestone with tasks within those milestones. My task dependencies are all accurate and the milestones appear in my schedule in a linear fashion based on the start and end dates. However, once I navigate away from my project schedule window and return, it appears all of my tasks and milestones shift into a random order not paying any attention to the start and end dates. Any help would be great!

Ian Smith Answered

Please sign in to leave a comment.

1 comment

0
Avatar

It seems that you have a sort or filter in place here. Please look at your column headers and see if there is a blue underline on any of them.  Click on the right of the header to clear sorts and filters, and that will put your project back into the original order.