After setting up a template and establishing dependencies...

After setting up a template and establishing dependencies, if someone manually changes the Start Date or End Date, does the system respond by resetting the other dependent start dates/end dates?  I am not experiencing this.  What do I need to do to have the dates cascade?

Kirsten Van Hoy Answered

Please sign in to leave a comment.

3 comments

0
Avatar

Hi Kristen,

 

When you manually set date, all the dependencies should change if there are no other manually set dates on the work items. If you have manually set dates on other work items, it will not cascade.

Tom Do 0 votes
Comment actions Permalink
0
Avatar

Is this true with Milestones as well, if I have manually set the dates of the milestones, changes to start dates of tasks won't cascade?

Tonaya Craft 0 votes