How can I change resource availability (% Units)

Afternoon,

 

I want to change % available from 100% to 80% for a resource, throughout the entire project.  How do i do this without going to every single task?

 

Thanks

Martin Jubb Answered

Please sign in to leave a comment.

6 comments

0
Avatar

You can specify the Resources' 'Maximum Project Availability'. This field is accessifble from the Resource Panel within the Project. You can maximize the panel for a better view. The default is 100%

Boris Krutiy 0 votes
Comment actions Permalink
0
Avatar

Hi Boris,

I'm aware that I can set maximum availability, but it looks like that only applies to new tasks and does not update existing tasks.

Thanks

Martin Jubb 0 votes
Comment actions Permalink
0
Avatar

Correct, that will have to be done manually at the Resource Panel Unit%

Boris Krutiy 0 votes
Comment actions Permalink
0
Avatar

How do I adjust the 100% default for Maximum Project Availability for all Projects (not just within the project)?

Jonathan Lang 0 votes
Comment actions Permalink
0
Avatar

There is a default project availability field if you go to a user's personal calendar in Clarizen.

Josh Santos 0 votes
Comment actions Permalink
0
Avatar

So in order to adjust default availability for everyone in the system (100+ people), I need to go into each and every resources calendar to change their %availability?

Emily Triyonis 0 votes