How do I access the project calendar to verify work week is set up correctly?

duration is auto adjusting to 7.88 in place of 7 d.

Monica Olguin Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Monica,

There are multiple Calendars you should reference. The first is at the Organizational level calendar. Go to Settings --> Global Settings to Edit the Calendar. You can also change Caledar settings at the Project, User and Group levels.