Project Utilization Report Types

Hi everyone,

 

When running the project utilization report, what is the difference between "working resources breakdown" and "all resources breakdown" on the project type? 

 

thanks!

Virginia

Virginia Hoskins Answered

Please sign in to leave a comment.

2 comments

0
Avatar

Hi Virginia, 

 "Working resources breakdown" = Report will only show resources who have work assigned to them on that specific Project, and Timeframe. If no Work has been assigned to a resources for the time period, one will see only resources who reported time at any given point during the Project.

 "All resources breakdown" = Report will show all resources, including Work Item Managers with no direct work assigned to them. 

Makes Sense? 

Yossi Truzman 0 votes
Comment actions Permalink
0
Avatar

hi Yossi,

 

Thanks for the feedback on this.  Is there an option to run this report so that inactive resources do not appear on the resource breakdown?

 

Thanks!

Virginia

Virginia Hoskins 0 votes