Post

1 follower Follow
0
Avatar

Task Showing up on Timesheet from previous week

A task that was from last week is showing up on this weeks timesheet.  How do I get is to stay with the date that is was due and not carry over?

Stacy Zellner Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Stacy, 

Is the Task still Active (not Completed)? If this is the case, it will continue to show until completed. If this is not the issue, please provide a screen capture showing the Timesheet view and highlight the Task that should not be there. Then provide a secondary image showing the Task properties (specifically Resources, STart/Due date, %complete, actual effort and remaining effort). 

 

Sincerely, 

Boris

Boris Krutiy 0 votes
Comment actions Permalink