What is the impact to an existing project if changing from Fixed Duration to Fixed Work?

What happens if you make this change to an existing Active project?  What gets recalculated/modified?  

Denise Stokowski Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Hi Denise,

Changing the work policy from Fixed Duration to Fixed Work shouldn't recalculate anything, it should impact project changes going forward.

For example, if you're now fixed work, then calculations going forward will assume that planned work is not flexible and the system will adjust the schedule/resources in order to meet the fixed work requirement.

Please let me know if you have further questions.