How can I edit the "work" field on a project without adding tasks?

For example, we planned out many projects for the next quarter. We estimated the effort days (which I would put into the "work" field) but haven't planned out tasks and subtasks. It seems the only way the general project "work" field only gets populated once tasks are added in, but is there anyway to edit that without tasks?

 

Thanks a lot!

Sima Vasilver Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Hi Sima,

Thank you for reaching out.

You will be able to update Work on tasks (child items only). The work column is locked at the project/milestone level as the work value is a roll up from subitems (tasks).

For further clarification, please join our Q&A webinars (see the link-> http://www.clarizen.com/resources/online-demo.html#second ).These are great resources for free consulting with our Customer Success Managers and visual answers to your questions. One of our experts will be able to discuss your specific business requirements and suggest best solution accordingly.

All the best,

Diana

Diana Sandura 0 votes