Is there a way to have the 'Work' field convert values to days?

Some of our projects uses hours in the 'Work' field, others use days. Is there a way to have all the values converted to days in the Projects - Portfolio view?

Nicolene Hart Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Hi Nicolene,

Out of the box, there isn't a way to do this. It's based on the unit that is used at the leaf level work item.

There may be a way to do this with Customizations. Here are 3 resources that we offer to help you handle customizations:

  1. Reach out to your dedicated CSM if you have one

  2. Post to our Customizations Q&A Forum where our customization experts respond and monitor regularly - https://success.clarizen.com/forums/22175706-Customizations

  3. Attend our Advanced Q&A session currently available a couple times per week - http://www.clarizen.com/resources/online-demo.html#second