Best Pratice - How to Share a next 2 to 4 weeks tasks of Project plan

Looking for best practice on how to share next two/three weeks of tasks with customers.
In order to keep the focus on next 2 to 4 weeks. We would like to show next 2-4 weeks plan each week with Customer Project manager so they can prepare their team. Can we select tasks in Project Schedule and share only that part?

Avnish Bhardwaz Answered

Please sign in to leave a comment.

1 comment

1
Avatar

Have you considered making reports that filter the next 2-4 weeks of the data you wish to show and collect that in a Dashboard? You can then either share the Dashboard with them as a Widget, link (if he has the required access) or as a pdf report.