Updating Two Resources on a Task

We have two resources assigned to one task. If each resource updates their task as 100% when they're complete will Clarizen interpret and change it to 50% for each person?

Thanks.

Pam Dye Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Pam, 

This depends on system settings. You will only get this information in the Related Resource Panel by showing the appropriate columns (% Complete, Actual Effort, etc) and if the Task 'Leaf Tasks Progress Reporting Policy' is set to Individual. Then % Complete at the Related Resource panel will update accordingly. if the mentioned setting is specified for Shared (default) instead of Individual, you will not get the same behavior.

Boris Krutiy 0 votes