Clarizen Regional Calendar Changes

In Clarizen the calculation of duration field is based on Organization Calendar . The business requirement is that the duration field should also calculate for  Regional calendar. 

Gupta, Bishal Not planned

Please sign in to leave a comment.

3 comments

0
Avatar

We need a new feature request in the application where clarizen should allow us to select calendar for the Project as well. In a Global organization, there could be some projects which follow calendar of different regions.

Currently the push of dates after setting duration takes only global calendar leaves in account. When is Clarizen Planning to have a CR number for this request?

Wasim Khan 0 votes
Comment actions Permalink
0
Avatar

Thank you for submitting your idea! For future request, the feature request ID is CR-409860.

Diana Sandura 0 votes
Comment actions Permalink
0
Avatar

I had a similar issue. so I set the base calendar for me project on the group calendar ( a regional calendar in your case). further to that, the group calendar's base calendar is the organization calendar. so any holiday in both calendar will be accounted for in my project. 

 

Tim Alkhatib 0 votes