Hi - I created a custom field on the Project Object using Relations Summary. My goal is to capture the sum of time tracked to a project that is marked as non-billable. I know there is time tracked to all of my projects that is flagged as non-billable however no data is populating in the field. Can someone help me figure out what I'm doing wrong?

 

Monica Brucks Answered

Please sign in to leave a comment.

2 comments

0
Avatar

I think that may be too heavy of a rule to run as a relations summary. I would speak to your PS Consultant or CSM, you may need to use workflow rules to calculate this.

Josh Santos 0 votes
Comment actions Permalink
0
Avatar

I was able to get this to work using Rollup functionality instead. 

Monica Brucks 0 votes