Multiple Resources Assigned to One Task

I have 3 resources assigned to one task, each with a different number of hours to complete.  2 have finished their work and so they need this task to no longer appear on their timesheet.  However, the task needs to stay open until resource No.3 has completed the work.  Am I able to do this?

Import from old forum Answered

Please sign in to leave a comment.

2 comments

0
Avatar

The task will appear in all of their timesheets until it is 100% complete. What you can do is split the task into 3 subtasks that are reportable, that way each will fall off when the user completes their portion of the overall task.

Clarizen Team 0 votes
Comment actions Permalink
0
Avatar

It would be great if there was a view filter at a task level to hide items that are not executable for me as I have already completed my part.  

Deborah Washburn 0 votes