Is there a way to prevent assigned resources from reporting time (on the time sheet) on completed tasks?

Thanks.

Import from old forum Answered

Please sign in to leave a comment.

1 comment

0
Avatar

There sure is. Just go to settings >> system settings >> time tracking, and uncheck "allow reporting on completed items"