All you need to do is right click on the project and resave that baseline. It will then be overwritten with the new dates.
Comment actions
Please sign in to leave a comment.
All you need to do is right click on the project and resave that baseline. It will then be overwritten with the new dates.
What do I do if I want to totally remove the baseline? (and show no baseline?)
There is no formal function for this, but you can save the project as a template and then create a new project from that template. This will remove the baseline entirely.
Thank you Josh.