All you need to do is right click on the project and resave that baseline.  It will then be overwritten with the new dates.

Clarizen Team 0 votes
Comment actions Permalink
0
Avatar

What do I do if I want to totally remove the baseline? (and show no baseline?)

Import from old forum 0 votes
Comment actions Permalink
0
Avatar

There is no formal function for this, but you can save the project as a template and then create a new project from that template. This will remove the baseline entirely.

Clarizen Team 0 votes