How to have man hours (work) override start end date?

How can I have the "hours" I input in the Work column override the start/due date columns? 

Here is an example: I have a task which will take 4 hours but the "Start date" is Dec 11 and the "Due date" is Dec 15. When I input this, Clarizen automatically adjusts my "Work" column to 40h or 5d. 

Problem is that this is not my case. The 4 hour task needs to be done within that period and I don't know how to reflect this. 

Any help ASAP please? 

Cheers

Angelina

Import from old forum Answered

Please sign in to leave a comment.

1 comment

0
Avatar

I would set the work items to fixed work, make sure to enter work first when building out a project, and also attend a Q&A forum to better understand how work and duration related to the date fields (http://www.clarizen.com/resources/online-demo.html).  Duration is always the difference between start date and due date, so likely changing the dates is modifying the duration, and in a fixed duration environment--which is the default--this will change what you have in the work column.

Clarizen Team 0 votes