Krystal,
Is the task dependent on another task? If so, you can set a "lag" when you set the dependency. This lag can be a negative number, e.g. -7 days, which in effect gives you lead time (the lag will cause the task start date to be the predecessor's due date - 7 days).
If you have further questions or information on the use case, please add a further comment to the thread, or join a free intermediate Q&A webinar (4 times a week for US time zones).