Hi Bo, this is not a rollup field but what you can do is use a customization to capture this information at one of the hierarchical levels in the project and roll it up through that customization. I would recommend hopping on one of our Advanced Q&A webinars to see this in action: http://www.clarizen.com/resources/online-demo.html
Post
Followbaseline cost roll up
Hi,
I understand baselines are saved depending on what level the project is chosen. However I want to know if the field "baseline cost" can be rolled up like the "work" and the "planned expenses". Is it possible? Thanks,
Bo
Please sign in to leave a comment.
4 comments
Date
Votes
Comment actions
Josh,
Thanks for the reply. That is indeed my plan once you confirm this system field is not designed to roll up. I had issues in dealing with roll up field where you can only update a roll up field if it is a leaf work item, is that correct?
Bo
Comment actions
Bo, that is correct, roll up fields can only be updated on the leaf work item.
Ariel
Comment actions
Thanks Ariel. I've setup the rule to only update leaf item and roll up to the parent.