Duration units and due date calculations?

When creating a task with work = 1 hr and a duration of 1day the due date is the Start date +1 and in other projects a similar task the due date = the start date?  Are there any settings I may check to be consistent when calculating my due dates?

Also, when changing the during to units from days to hours in the Start date + 1 scenario, I have to have a duration of at least 2hrs until the task due date = the start date.

 

Any help understanding the differences is greatly appreciated.

 

Thanks,

Stalin 

 

Stalin Pumisacho Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Are you using dependencies? It is very possible that a dependency would push a task to the next day. It could also be differences between project or resource calendars.

Josh Santos 0 votes