I am having trouble getting my tasks to flow correctly in the gantt view

Specifically, I am not understanding how to properly assign work vs duration such that the project runs over the 90 day launch period.

Jeff Thompson Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Work does not impact the Gantt at all, only duration (the difference between Start and End dates).  I think you are going to have to be a bit more specific with your question.  Increasing the duration or spacing out the dates should get you to the schedule you are looking for.