This can be a very complicated topic, I would recommend hopping on one of our interactive Q&A webinars to fully understand how work, duration, unites, start date, due date, and dependencies all work together (http://webinars.clarizen.com).
Post
FollowStrange behaviour on task
Currently I've made a test project. Which one open active task.
remaining effort 8 hours. A resource is added to the task with an "project maximum availability" of 0.2 FTE (=20).
So that's 2 hours a day, and the task should take 4 days to be completed. But Clarizen is not recalculating the end/due dates.. The earliest end date remains also on the same day.
Another problem arises when task 1 is competed earlier than the Due date with a FTS dependancy between task 1 and 2. This should give me a message that we can proceed earlier to task 2. Or reschedule the upcoming due date for task 2 with my approval.
Its probably a setting, but please show us how this has to be implemented to make this work.
Feel free to contact me. My contact details are listed below.
Niek Smits
Project Manager
ControlPay b.v.
Office: +31(0)76 599 1590
Mobile: +31(0)6 4641 457
Please sign in to leave a comment.