How do I clear the % complete on an entire project

Hi,

I've copied a project that is in progress to use again, and I want to clear all the % complete for the entire project on all tasks.

but I can't seem to copy down the %complete column like I used to in V5.  can you tell me how to do it in one action, instead of having to do each task individually?

 

thanks,

Janet

 

Janet Answered

Please sign in to leave a comment.

2 comments

0
Avatar

Hi Janet,

You can click on one task and change the % completed to 0, then use Ctrl+C/Ctrl+V (copy&paste) to copy this value to the rest of the tasks.

Please note that there's a template feature you can use also for similar purposes.

 

Tamir Avital

Customer Success Manager

Tamir Avital 0 votes
Comment actions Permalink
0
Avatar

You might need to expand the work plan. If it’s not expanded you're probably trying to set % on hammocks, which rollup from sub items. 