We have a Clarizen users who is a resource on a sub task but she is unable to modify the task name or the dates.  It shows the lock symbol on those fields.  What setting are we missing that would allow her to edit those fields as a resource?  Thanks.

Suzanne Fielden Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Hi Suzanne,

A resource can't change the task properties, just the amount of effort (actual, remaining etc.). If you want a resource to be able to do that you should also assign the user as the task manager.