I have a task planned for 1 day, but the calculated schedule has it finishing the day after it starts. Other 1 day tasks in the plan finish on the same day that they start. What would cause the task to be scheduled over 2 days? How can I correct it?
Thanks,
Richard
Please sign in to leave a comment.
Actually, I found the cause. It was a 1 hour task earlier in the plan. Issue solved. Thanks.
So it had a predecessor that was one hour long? That would be the culprit.