Task with 1d duration scheduled over 2 days?

I have a task planned for 1 day, but the calculated schedule has it finishing the day after it starts.  Other 1 day tasks in the plan finish on the same day that they start.  What would cause the task to be scheduled over 2 days?  How can I correct it?

 

Thanks,

Richard

Richard Udy Answered

Please sign in to leave a comment.

2 comments

0
Avatar

Actually, I found the cause.  It was a 1 hour task earlier in the plan.  Issue solved.  Thanks.

Richard Udy 0 votes
Comment actions Permalink
0
Avatar

So it had a predecessor that was one hour long? That would be the culprit.

Josh Santos 0 votes