Hi,

What does it mean when a task in a project has the icon - executable?

see attached

 

thanks,

Janet

 

Janet Answered

Please sign in to leave a comment.

3 comments

0
Avatar

Executable = active task with completed Predecessors.

 

Tamir Avital

CSM

Tamir Avital 0 votes
Comment actions Permalink
0
Avatar

Advanced permissioning uses the executable flag for the validation rule "Prevent reporting for non executable work items" to prevent new entries on timesheet for non executable work items that have actual effort updated from timesheet. As a result, time entry is only possible on active tasks when the predecessors have been completed. We decided to disable this validation rule.

Sander Schijvens 0 votes
Comment actions Permalink
0
Avatar
  • Every work item in Clarizen can have an “executable” flag displayed on it.
  • The Executable flag is shown when a work item can be worked on. Executable tasks are Active Tasks that have no active predecessors.
  • When you set dependencies (most commonly Finish to Start dependencies), you can chain tasks together logically and chronologically so that each task will only become executable when tasks that need to be completed
    before (predecessors) have been completed. This allows resources to prioritize tasks.
Norbert Atienza 0 votes