Post

1 follower Follow
0
Avatar

Which Project field contains the EAC Hours? I'm looking for the field that has Actual Effort + Remaining Effort = EAC Effort. The EAC field has the comment "CurrencyEAC" and is numeric.

I'm looking for the field that has Actual Effort + Remaining Effort = EAC Effort. 

The EAC field has the comment "CurrencyEAC" and is numeric, so that is not it.

Eric Marking Answered

Please sign in to leave a comment.

3 comments

0
Avatar

All you need to do is create a new formulaic field that is Actual + Remaining Effort.

Josh Santos 0 votes
Comment actions Permalink
0
Avatar

Thanks for the quick response.  Is this a custom field?  Unfortunately, we are on professional and have already used our 3 custom fields. 

I would have expected that the Effort At Complete (EAC) and Variance At Complete (VAC) (which is Actual Effort + Remaining Effort- Work) would be part of the standard field set as they are universally used (and described in PMBOK in much detail).

Are there really no other way to get to these values?

Thanks

 

Eric Marking 0 votes
Comment actions Permalink
0
Avatar

Yes, you would need a custom field for this unfortunately :/

Josh Santos 0 votes
Comment actions Permalink