Hello,
I'm sharing a Gantt View with my customer and I would like to add the "Resources" column to that view.
It doesn't make sense to him (the project sponsor) no to see wich of the tasks are their responsability. How can I configurate the columns on a shared Gantt view?
I'm sending the image attached, so you can see the view.
Thanks in advance,
Michel Rozenberg
Please sign in to leave a comment.
4 comments
Date
Votes
When I expand 'Work items', I only see Milesone, Project, Tasks....no Gantt Columns. Is there any other way I can find Gantt Columns .. Gant Widget Columns?
Hello,
You would need to go to "Settings" first and click on "Layout". After that, highlight "Work Items" and in the middle panel, you should be able to edit the columns. Please see my screenshot.
Tom I got it, thank you!