When something is in draft, you will not see the scheduling status of that item (no red, yellow, green indicators) and no system notifications will be sent out to that user asking him/her to update their progress. If something is in execution, the best practice is for it to be set as active. Keep in mind that you can have multiple states set throughout a project (one milestone can be completed while another is being executed and yet another is still in planning).