The Mark As function to change the state currently works for all children objects (milestones or tasks) of that project but do not affect sub projects.  Is there a setting that can be changed to allow this or do we need to create a custom action in order to change the state of the sub projects to match the main project?

Tori Meek Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Hi Tori,

Correct, that is out of the box behavior. You'll need to build a workflow rule that automatically updates sub-project 'state'.

For assistance, please attend our advanced configuration 'Office Hours' - http://www.clarizen.com/live-demo.html#second

Or you can also post to our Customizations Q&A.