Most Effective Way to See Unassigned Tasks?

I know that if I don't assign a resource I get an alert about it.  However, is there a recommended way to easily see all active tasks across projects for which a resource has not been assigned?  I suppose I could create a custom task view or a report?  What would you recommend?

Ideally it sure would be nice if when I selected Task Team View in addition to the generic "everyone" option on the left there was an "unassigned" option.

Thank You

Project_Manager Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Unassigned option is not available but you can filter on this by creating a filter in Task module like this...

Resource = <Blank>

Even easier may be to go to the Resource column, click on the icon to the Right of the header to change the Filter/Sort and specify Filter 'Blank'. This will show you only Tasks where the Resource field is Blank.

Boris Krutiy 0 votes