Post

1 follower Follow
0
Avatar

move task level

To move a task to be a sub task in MSP I just select and move it or I can hit the toolbar icon. I cannot find out how to do this in Clarizen

Patrick Duffy Answered

Please sign in to leave a comment.

2 comments

0
Avatar

Hi Patrick,

In the Work Plan panel, select the work-item that you want to move as a 'sub-task' and click "indent".

You can also drag and drop tasks in the work plan with the grey squigglys along the left border. See screenshot: http://screencast.com/t/R0Ieio5LAsJb

Permanently deleted user 0 votes
Comment actions Permalink
0
Avatar

Message by customer was caught by spam...

 

Vanessa the “indent” works. Had real problems finding it though. Needs to be an icon on the main bar Indent/Outdent You can only drag and drop tasks at the same level, not indent them. Regards Patrick Duffy 

Boris Krutiy 0 votes
Comment actions Permalink