How do I set a lead of a specified number of days while creating a dependency between milestones?
There is a provision for creating a lag while setting up the dependency, but what should be done to introduce a lead. Scenario
Current
FINISH to START dependency is set up between Milestone 1 and Milestone 2
Milestone 1: Initiation (start date: 01/01/2015- 01/30/2015
Milestone 2: Requirements (start date 01/31/2015- 02/15/2015)
Expected
FINISH to START dependency is set up between Milestone 1 and Milestone 2
Lead : 10 days
Milestone 1: Initiation (start date: 01/01/2015- 01/30/2015
Milestone 2: Requirements (start date 01/20/2015- 02/05/2015)