Official comment
You would have to re-baseline the whole project. You cannot just edit the financial fields on the original baseline.
Comment actions
We have a baselined project. Our client has executed a change order that adds additional budget for the project. How do I model this in Clarizen so that the baseline is updated to reflect the additional budget?
You would have to re-baseline the whole project. You cannot just edit the financial fields on the original baseline.