How can the baseline for a project be updated to reflect additional budget authorization

We have a baselined project. Our client has executed a change order that adds additional budget for the project. How do I model this in Clarizen so that the baseline is updated to reflect the additional budget?

Tschaeffer Answered

Official comment

Avatar

You would have to re-baseline the whole project. You cannot just edit the financial fields on the original baseline.